Municipal Hall Project Progress Update

Municipal Hall Project Notices, Weekly updates, and bi-monthly Council update reports will be updated on this page.


Weekly Updates and bi-monthly Council Update Reports.
 

Nov 29 - Dec 5

 
Site Clearing
  Dec 6 - 10
 

Excavation for the new North Wing completed and Building Permit issued

  Dec 13 - 19
  Excavation and site preparation
  Dec 20 - 26
  Prepare and pour footings
  Dec 27 - Jan 2   Prepare forms for foundation
  Jan 3 - 9   Finish preparing foundation forms and pour concrete for the foundation walls
  Jan 10 - 16
  Strip foundation walls and backfill
  Jan 17 - 23
  Complete plumbing and electrical subgrade rough in and complete back fill compaction
  Jan 24 - 30   Concrete slab poured.  Wood framing for the new south wing commenced
  Jan 31 - Feb 6
  Framing continues for the new south wing
  Feb 7 - 13
  Framing continues for the new south wing
  Feb 14 - 20
  Framing continues for the new south wing
  Feb 21 - 27   Framing is completed and roofing begins
  Feb 28 - Mar 5   Install windows and begin work on building envelope
  Mar 6 - 12   Start rough in of plumbing, electrical and mechanical equipment and continue work on building envelope
  Mar 13 - 19   Work continues on installing windows, building envelope, rough in of plumbing, electrical and mechanical equipment, and work has started on insulation and drywall boarding
  Mar 20 - 26   Work continues on building envelope, rough in of plumbing, electrical and mechanical equipment and on insulation and drywall boarding.  Work has begun on removing the exterior wall separating the new south wing and the existing building
  Mar 27 - Apr 2
  Work continues on the building envelope and insulation and drywall
  Apr 3 - 9
  Work continues on the building envelope and insulation and drywall
  Apr 10 - 16   Work continues on the building envelope and insulation and drywall
  Apr 17 - 23   Drywall completed, painting started, electrical room consolidation and upgrade to three phase underway, cabinet work started and installation of the Solar Panel field at the front of the Municipal Hall property began.
  Apr 24 - 30   Exterior wall cladding continues. Interior mechanical and electrical work continues including ventilation, heating and lighting. Drop ceiling frame installed. Conversion of electrical service to three phase continues.
  May 1 - 7   Carpet installed.  Exterior wall cladding continues.  Interior mechanical and electrical work continues including ventilation, heating and lighting.  Conversion of electrical service to three phase continues.
  May 8 - 14   Interior lighting and doors installed.  Floor tiles installed.  Mechanical and electrical work continues and exterior finishing continues.
  May 15 - 21
  Second coat of painting and trim painting. Counters installed. Millwork and finishing continues. Exterior painting and trim continues.
  May 22 - 28   Interior trim painting, finishing and millwork continues.  Exterior painting and trim continues.
  May 29 - Jun 4   Interior finishing continues.
  June 5 - 11   Interior finishing continues. Hydro conversion from single phase to three phase power begins. Parking lot expansion preparation begins.
  June 12 - 18
  Electrical conversion works and finishing continue.  Parking lot and sidewalk improvements started.
  June 19 - 25   Electrical conversion and finishing continues.  Paving completed.
  June 26 - July 2
  Electrical conversion and finishing continues.  Renovation to north wall and offices begins.
  July 3 - 9
  Phase one finishing continues.  Electrical conversion to three phase power completed.  Moving from old wing to new wing commenced.
  July 10 - 16   Move from old wing to new wing completed. Occupancy certificate for phase one secured July 11, 2016.  Preparation for demolition of old wing commenced.
  July 17 - 23   Restoration work on the north wall continues. Demolition and hazardous material removal begins for phase two.
  July 24 - 30
  North Wall repairs continue.  Demolition and hazardous material removal continues.
  July 31 - Aug 6   North Wall repairs continue.  Demolition and hazardous material removal continues.
  Aug 7 - 13   North Wall repairs continue.  Demolition and hazardous material removal continues.
  Aug 14 - 20   North Wall repairs continue.  Demolition and hazardous material removal continues.
  Aug 21 - 27   North Wall repairs continue.  Demolition and hazardous material removal continues
  Aug 28 - Sep 3   North Wall repairs continue.  Demolition and hazardous material removal continues
  Sep 4 - 10   North Wall repairs continue.  Demolition and hazardous material removal continues
  Sep 11 - 17   North Wall repairs continue.  Demolition and hazardous material removal continues
  Sep 18 - 24   North Wall repairs continue.  Demolition complete and excavation begins
  Sep 25 - Oct 1   North Wall repairs continue.  Site preparation and cribbing for replacement wing begins
  Oct 2 - 8   North Wall repairs continue.  New wing footings cribbed and poured and foundation wall forming and pouring begun
  Oct 9 - 15   North Wall repairs continue. Foundation wall forming and pouring continue
  Oct 16 - 22   North Wall repairs continue. Foundation wall forming and pouring continue
  Oct 23 - 29   Slab preparation and slab pour
  Oct 30 - Nov 5   Complete pouring concrete walls and stripping forms
  Nov 6 - 12   Start framing
  Nov 13 - 19   Continue framing
  Nov 20 - 26   Continue framing
  Nov 27 - Dec 3   Continue framing
  Dec 4 - 10   Continue framing
  Dec 11 - 17   Continue framing
  Dec 18 - 24   Continue framing
  Dec 25 - 31   Continue framing
  Jan 1 - 7   Continue framing
  Jan 8 - 14   Framing continues and ground work
  Jan 15 - 21   Framing continues and slab preparation
  Jan 22 - 28   Framing continues and concrete slab poured
  Jan 29 - Feb 4   Framing continues and roofing begins
  Feb 5 - 11   Framing and roofing continues